Bihar News: Electricity supply affected in Buxar, restoration started through alternative arrangements.

Bihar News: To restore the affected power supply in some areas of Buxar district of Bihar. Bihar State Power Transmission Company Limited (BSPTCL) Has made alternative arrangements. Installed in 132/33 KV grid substation located in Dumraon Technical fault in 80 MVA power transformer After the arrival, power supply was affected in some rural and urban areas. Technical teams were immediately sent to the spot and arrangements were made to provide electricity through alternative means.

Technical fault in Dumraon grid

Managing Director of BSPTCL Dr. Naval Kishore Chaudhary Said that after the technical problem came to light in Dumraon grid sub-centre, instructions were given to identify it quickly and take necessary steps. Company teams were immediately sent to the spot to deal with the emergency.

Using available resources, alternative arrangements were made, due to which power supply is being restored in the affected rural and urban areas of Buxar district.

Alternative arrangement for about 45 MW electricity

According to the company, 132 kV double circuit line from GSS Dumraon (New) to Dumraon close at 33 kV through 30 MW power Arrangements have been made for supply.

Apart from this, GSS Dumraon (New) Additional 15 MW power from 33 kV feeder Arrangements are being made to provide it. In this way, available alternative means are being used to provide electricity to the affected areas.

Repair and testing of faulty transformer continues

The repair work of 80 MVA power transformer having technical fault is being done by the manufacturing company. Along with this, necessary testing is also being done at a rapid pace, so that the problem can be completely resolved and normalcy can be restored.

According to BSPTCL, the technical team has identified the problem through inspection and mutual coordination.

Preparation to install another 80 MVA transformer

As well as repairing existing transformers. To install additional 80 MVA transformer at Dumraon Grid Substation Action is also being taken. This is expected to provide additional support to the grid capacity and supply system.

The Managing Director said that BSPTCL is committed to providing uninterrupted and quality electricity to the consumers. After the situation is completely stable Normal routine power supply resumed Will be done. Till then, all necessary steps are being taken to ensure that consumers face minimal problems.