Rivoi News, November 21, 2026 – Bullet Train: Overhead electrification In a significant milestone in India's first Bullet Train project, the Overhead Equipment (OHE) system in the Surat – Bilimora section of the Mumbai – Ahmedabad Bullet Train Corridor was successfully energized on 20 November 2026.
To ensure safety and adherence to prescribed procedures, energization will be done in a phased manner in small sections under strict supervision of technical teams.
Also read: Voters whose names are not included in the voter list will be able to get their names registered by filling Form 6.
This section includes both up and down lines on elevated alignment. This project marks an important step towards further testing activities. A state-of-the-art 2 × 25 kV overhead traction system has been installed in the Mumbai-Ahmedabad Bullet Train Corridor. It is one of the most advanced electrification technologies used in high-speed rail systems around the world.
Traction Sub-Stations (TSS) have been established at a total of 14 places in this 508 kilometer long corridor. These sub-stations will draw electricity from the national grid and provide electricity to the overhead traction system to operate high-speed trains. The installation work of control panel, changeover switch, transformer and circuit breaker building has been completed in the first traction sub-station of Bilimora in Navsari district of Gujarat.
Also read: Award to Ahmedabad Municipal Corporation for its excellent performance in the implementation of PM-Swanidhi Scheme.
The TSS located in Gujarat will be supplied power from the 220 kV Ambetha Grid sub-station of Gujarat Energy Transmission Corporation Limited (GETCO).
The entire electricity network will be monitored by a centralized control center to ensure safe and reliable operation.
The Surat–Bilimora section consists of an approximately 50 km long elevated alignment between the two stations. This alignment also includes bridges built on four rivers and a steel bridge on National Highway-53 (NH-53). To reduce the impact of noise in the surrounding areas, approximately 94,000 noise barriers have also been installed on this viaduct.
public safety advisory
When the overhead electrical system is energized, citizens living around the alignment, passengers, construction workers and general public are strictly advised not to go near the overhead electrical equipment, try to touch them or do any unauthorized work around them.