Business Desk – Adani Energy Solutions Share: The company will buy 100% stake of Vikramshila Power Transmission Limited. For this, an agreement has been signed with REC Power Development. After the news, there was a rise in the stock in initial trading, but later it came down to the red mark.
Investors are keeping an eye on the shares of Gautam Adani's company Adani Energy Solutions today i.e. on 23rd November. The company has won the power transmission project associated with the 2,400 MW Pirpainti Thermal Power Plant in Bihar.
For this, the company has signed an agreement to purchase 100% stake of Vikramshila Power Transmission Limited (VPTL). This deal has been done with REC Power Development and Consultancy Limited.
On Monday, the company's shares opened with gains in early trade, but by the time the news was written, it had declined and was trading in the red.
How will Adani Energy Solutions make the acquisition?
The company said that it will buy the entire stake of Vikramshila Power Transmission Limited by paying cash. The face value of each share of VPTL is Rs 10. This company was established on 24 August 2026.
Due to its recent establishment it has no declared turnover yet. Through this acquisition, Adani Energy Solutions will expand its power transmission business in Bihar.
Two 400 KV substations will be built in Bihar
Under this project, the company will build two 400 KV substations in Jhanjharpur and Begusarai in Bihar. Through these substations, the electricity generated from the 2,400 MW Pirpainti Thermal Power Project will be transported to other areas.
The project also includes power transmission lines of 400 KV, 220 KV and 132 KV. This is expected to help in strengthening the electricity transmission network of Bihar and making the electricity supply more reliable.
Adani Energy Solutions' presence will increase in Bihar
This acquisition will increase Adani Energy Solutions' presence in the power transmission sector of Bihar. The company's new project will play an important role in delivering electricity from Pirpainti Super Thermal Power Plant to the state's power grid.
This project is considered important in view of the increasing demand for electricity in Bihar. This can increase the capacity to supply electricity to different areas of the state.
Why are investors keeping an eye on the stock?
The company is expected to expand its transmission business with this new project. However, the fall in the stock after the initial rise shows that investors are assessing the news as well as its financial impact.