New Delhi, 24 November 2026: Union Railway Minister Ashwini Vaishnav had said that India's first bullet train project has reached a very important milestone. The trial run on the Surat-Bilimora section of the Mumbai-Ahmedabad high-speed rail corridor is expected to start from May 2027. This approximately 50 kilometer long section will be the first part of the country's first high-speed rail corridor, where the bullet train will be tested. This is being considered a big step towards starting high-speed rail service in India.
According to the Railway Minister, the signaling work on the Surat-Bilimora section is likely to be completed by January next year, while the electrification work has already been completed. On 20 November, the overhead devices on both the Up and Down elevated lines of this section were successfully charged. Vaishnave informed that 2×25 KV traction system is being used in the entire corridor and the installation work at Bilimora traction sub-station has also been completed.
Bullet train service will start in phases
Ashwini Vaishnav said that the Mumbai-Ahmedabad Bullet Train Project will be started in a phased manner. The Ahmedabad-Vapi section is targeted to be completed by the end of 2027, while there are plans to extend bullet train services to Thane by 2029. The initial trials will be done with the 'B-28' trainset, which is designed to run at speeds of up to 280 kilometers per hour. The Railway Minister said that rail services with speed more than 240 kilometers per hour fall in the high-speed rail category and require special engineering and construction standards for their operation.
The Railway Minister said that the air pressure generated by trains running at high speed is one of the biggest technical challenges. This enables the train and its associated structures to withstand extreme pressure. He said that the B-28 train has successfully passed the 'squeeze test'. During this test, almost double the air pressure generated during normal operation was applied on the train. The success of this test has helped ensure that the train can operate safely in high-speed conditions.
Undersea tunnel work continues at fast pace in Maharashtra
Vaishnave had informed that construction work is progressing rapidly in parts of Maharashtra, which also includes the undersea tunnel. Under this project, high-speed rail network is being prepared using state-of-the-art technology and special engineering standards.
It is noteworthy that last week Vaishnav had said that the 508 km long Mumbai-Ahmedabad high-speed rail project has now moved beyond the planning stage and construction work is going on at a rapid pace at the ground level. The government aims to start the country's first bullet train service in the last quarter of 2027. After the completion of this project, the travel time between Mumbai and Ahmedabad will be reduced to less than two hours, which is expected to give a new impetus to connectivity and trade between the two main economic centers of the country.