Developer of Vietnam’s largest airport Long Thanh ordered to vouch for every flawed work item

In a conclusion notice issued by the Government Office on Saturday, Tuc required ACV, the airport developer, to clearly confirm the quality of each item where errors occurred during the project’s implementation.

“ACV bears full responsibility for the progress and quality of component project 3, the essential facilities within the airport, and the contract packages for which it is the investor,” the notice said.

The Ministry of Public Security was tasked with speeding up its investigation and handling of violations at the project, and clarifying the extent of the violations in each contract package and work item.

Police have placed 31 people under criminal investigation in connection with the project for offenses including violating bidding regulations, bribery and embezzlement. Former ACV chairman Vu The Phiet is among them.

The Ministry of Finance is to guide ACV in resolving problems with payments, financial mechanisms, price appraisal and the exchange rate used to pay for imported equipment.

ACV must submit a plan for a special mechanism to resolve the project’s obstacles to the Ministry of Construction before Dec. 5.

Tuc noted that the mechanism is meant to speed up progress, but it must clearly define the responsibilities of the parties involved, must not legitimize violations and must ensure technical safety.

Long Thanh International Airport under construction in Dong Nai City, October 2026. Photo by Read/Quynh Tran

At a meeting on Wednesday, ACV said construction of component project 3 was 88.6% complete, with disbursements at 57% of the contract value.

The project has nevertheless run into problems with acceptance and payment, because the investor and contractors did not follow certain procedures.

Some materials and equipment were switched to a different manufacturer, brand, type or origin from those in the contracts without ACV’s approval. Some items were built in ways that did not match the approved technical designs, or before the construction drawings had been approved.

According to ACV, resolving these issues is a prerequisite for formally accepting the completed works and licensing the airport to operate.

Because it cannot complete all the essential facilities in 2026, ACV has proposed extending the deadline for the airport’s first phase to 2027-2028.

Tuc asked ACV to review the remaining work and set clear milestones for completing construction, installing equipment, acceptance, test runs and the start of operations.

Under the investment policy approved by the National Assembly, the first phase of Long Thanh airport must be completed in 2026.

ACV had said it planned to begin operations on Dec. 24, increasing flight frequency gradually over three phases. However, several key packages, including the passenger terminal, cargo terminal No. 1, the parking garage and the airport management system, are not expected to be completed or finish test runs until June 2027.

Long Thanh, Vietnam’s largest airport project, is being built on about 5,000 hectares in southern Dong Nai City, 40 km east of Tan Son Nhat International Airport in Ho Chi Minh City. Its first phase is designed to handle 25 million passengers and 1.2 million tons of cargo a year.