Delhi Mumbai Expressway: These lands will turn into gold in Delhi-NCR, this expressway is being built

Delhi Mumbai Expressway: Central road transportation And Highway Minister Nitin Gadkari by Lok Sabha In Big Update give happened told That Delhi,Mumbai expressway Of dnd Junction From Jaitpur till Of First Part About Ready yes paid off Is, it Section Soon Will be opened only for the people.

dnd From Jaitpur till 9 km Package-1 almost ready

Minister Gadkari informed that 94% work of 9 km long Package-1 has been completed. This part was delayed because it took time to get the design of the bridge to be built on the Agra Canal approved. Approval has now been received and the construction work is in the final stages.

The government aims to fulfill Section It should be completely ready by June 2026.

71,718 crore spent

Delhi,Mumbai expressway India’s largest and most expensive highways Projects Is included in. So far Rs 71,718 crore has been spent on this. The entire highway will be of 8 lanes and after its construction, the journey from Delhi to Mumbai will be reduced from 24 hours to 12 hours.

Use of modern technology for the safety and convenience of passengers

expressway But modern technology and Smart The facilities are being used. upon its completion travel will be safer, Trains will be able to move at high speed without interruption And Tourism will also get a big boost,

Alwar Near helicopter service started

of Rajasthan under the project Alwar Near District 125 km ones rest Area In helicopter Service has also been started. emergency This service in case the injured Will help in taking him to the hospital immediately.

Road inspection completed, final improvements underway

Road quality inspection has been completed and work on minor improvements is continuing. The government wants that expressway Should be fully operationalized as soon as possible.

59 km of Delhi Section only one part left

dnd,Faridabad,59 kilometers from Sohna Section It is being built in three parts. Two parts are completely ready and open for traffic, now only the first Section ,dnd,Jaitpur) is left, the construction of which is continuing rapidly

Comments are closed.