Jal Jeevan Mission Scam: Two companies missing after taking Rs 254 crore for tank construction in 230 villages of Shamli district, DM summoned details
Shamli: Under the Jal Jeevan Mission Scheme in Shamli District of UP, work was given to two institutions named JMC Lakshmi and Gayatri. The most surprising thing is that Rs 254 crore has been released for this, but the companies have gone missing leaving the work incomplete. Let us tell you that after taking Rs 254 crore released for the construction of water tanks in 230 villages of Shamli District, two working companies are currently missing. According to the information received, work has been completed only in 56 villages in four years, while in 174 villages the construction work is incomplete and there is no one to take care of it. Taking cognizance of this matter, the District Magistrate has set up an investigation.
Read :- Jal Jeevan Mission Scam: Big action under CM Yogi’s zero tolerance policy, 12 engineers suspended, departmental inquiry against four, notice to three and transfer of seven.
Sources reveal that in the year 2022, tank construction work was started in all 230 villages of the district, for which a budget of about Rs 500 crore was approved. The contract for the construction work was awarded to two companies, to whom Rs 254 crore has been paid. Despite this, the work is incomplete in most of the villages. For the last one and a half years, construction has completely stopped at many places and the construction contractors and laborers are not even paying attention. The situation is such that whatever construction has been done is now falling into disrepair.
Shamli District Magistrate Arvind Kumar Chauhan, while asking for complete details, directed the officials to complete the incomplete works as soon as possible. Along with this, the question has also been raised that when Rs 254 crore out of Rs 500 crore has been released, then why was the construction work not completed? Instructions have been given to take action against the guilty companies.
Jal Nigam’s XEN Phool Kumar (XEN Jal Nigam) said that notices have been issued several times to the executing agencies JMC Lakshmi and Gayatri, but no response is coming. Efforts are being made to start work again. If the work does not start soon, action will be taken to blacklist the concerned institutions.
Problems of villagers increased due to incomplete construction
Read:- Anti-Corruption Bureau’s big action in Rajasthan in Jal Jeevan Mission scam, 15 accused including retired IAS Subodh Aggarwal on radar.
In Hasanpur Luhari, the road was dug up and abandoned in the name of pipe repair. There is a deep pothole in the middle of the road, which poses a risk of accident. Pipeline was laid in Kheda Bhau, but water is leaking from many places. The construction work of the tank has also stopped for several months. According to the information received, the tank was completed two years ago in Razzaq Nagar (Jhinjhana) and the pipeline has also been laid, but till now the water supply has not started. Villagers like Ramdhan and Rupin say that despite spending crores of rupees, they are not getting pure water. Work is also incomplete in Kairana, Gadhipukhta, Kandhla, Thana Bhawan, Chausana, Bidauli and Babri areas.
Work completed in these villages
56 villages including Adampur, Ahata Gosgarh, Asadpur, Aurangabad, Babri, Badhupura, Bahawadi, Barnavi, Barkhandi, Bhainswal, Bhainsani, Bhanera, Bharsi, Bhogi Mazara, Bibipur Hatiya, Butrada, Chadhav, Chausana, Dangraul, Dhanena.
There is incomplete work in these villages
174 villages including Lisadh, Lilaun, Garhi, Kudana, Sonta, Fatehpur, Garhi Abdullah Khan, Garhi Pukhta, Jalalpur, Jasala, Kabaut, Kadarpur, Kairi, Kajpura, Kheda Gadai, Kheda Mastan, Khedi Bairagi, Khanwada, Malakpur, Mundetkalan, Nala, Naunagli remain in a bad condition.