New Delhi, November 23 (IANS). Union Railway Minister Ashwini Vaishnav on Monday said India's first bullet train project has neared an important milestone. Trial runs on the Surat-Bilimora section of the Mumbai-Ahmedabad high-speed rail corridor are expected to begin from May 2027.
According to the Railway Minister, the 50 km long Surat-Bilimora section will be the first part of the country's first high-speed rail corridor on which the bullet train will be tested. This project is considered an important step towards India's high-speed rail travel.
He said that the signaling work on this section is expected to be completed by January next year, while the electrification work has already been completed. The overhead equipment on both the Up and Down elevated lines of this section were also successfully charged on 20 November.
Vaishnav said that 2×25 KV traction system is being used in the entire corridor and installation work at Bilimora traction sub-station has also been completed.
He informed that the Mumbai-Ahmedabad Bullet Train project will be started in a phased manner. The Ahmedabad-Vapi section is targeted to be completed by the end of 2027, while there are plans to extend services to Thane by 2029.
Initial trials will be conducted with the B-28 trainset, which is designed to run at speeds of up to 280 kilometers per hour. The Railway Minister said that rail services with speeds above 240 kilometers per hour fall in the high-speed rail category and require special engineering and construction standards.
He said that the air pressure generated by trains running at such high speeds is one of the biggest technical challenges. Therefore both the train and its associated infrastructure are designed to withstand extreme pressure.
Vaishnav said that the B-28 train has successfully passed the squeeze test. During this test, the train was pressurized to almost twice the air pressure created during normal operation. The successful testing proved that the train could operate safely in high-speed conditions.
The Railway Minister also said that the construction work in the Maharashtra portion, which also includes the undersea tunnel, is progressing rapidly.
It is noteworthy that last week Vaishnav had said that the 508 km long Mumbai-Ahmedabad high-speed rail project has now moved beyond the planning stage and construction work is going on at a rapid pace at the ground level. The government aims to launch the country's first bullet train service in the last quarter of 2027.
After completion of the project, the travel time between Mumbai and Ahmedabad will be reduced to less than two hours, which will give a new impetus to connectivity and trade between the two major economic centers of the country.
–IANS