Work is progressing on two important projects towards the expansion of the metro network in Delhi-NCR. The construction of eight elevated stations of the Golden Line corridor (Golden Metro Line) from Lajpat Nagar to Saket G Block in South Delhi is expected to start soon. The work of station construction on this approximately 8.385 km long route has been allotted for Rs 137.92 crore. A target has been set to complete it in 22 months. At the same time, the plan to build a new underground metro line from Rajiv Chowk in Gurugram to Yasho Bhoomi in Delhi has also received in-principle approval from the Delhi Government. Both these projects are expected to provide better metro connectivity to the passengers of Delhi and NCR in future.
Eight elevated stations will be built on the Golden Line
The Golden Line corridor being built from Lajpat Nagar to Saket G Block will connect many major areas of South Delhi to the metro network. Eight elevated stations will be built on this approximately 8.385 kilometer long route. A contract worth Rs 137.92 crore has been allotted for the construction of the station. The construction agency will have to complete this work in 22 months. The new corridor will improve the connectivity of areas like Lajpat Nagar, Andrews Ganj, Greater Kailash, Chirag Delhi, Pushp Vihar and Saket. This is expected to benefit the local residents as well as the people working and studying in these areas.
Golden Line will pass through these eight stations
According to DMRC, the corridor to be built from Lajpat Nagar to Saket G Block will include eight elevated stations. Mainly these stations are: Lajpat Nagar, Andrews Ganj, Greater Kailash-1, Chirag Delhi, Pushpa Bhawan, Saket District Centre, Pushp Vihar, Saket G Block. This corridor will help in connecting many major residential and commercial areas of South Delhi with the metro network.
Contract for seven stations for Rs 137.92 crore
The construction work of seven out of eight elevated stations of the corridor has been allotted for Rs 137.92 crore. The selected construction agency will have to complete the work within the stipulated period of 22 months. The construction of Lajpat Nagar station will be allotted separately. Thus, the plan is to complete the corridor within the stipulated time frame with the construction of all eight stations. The construction process of this part of the Golden Line started in December last year. Now work is also being carried forward in the direction of station construction. The project is targeted to be completed by June 2029.
Greater Kailash and Pushp Vihar will get the most benefit
This extension of the Golden Line will connect those areas of South Delhi with the metro network, where currently public transport options are limited. Residents of Greater Kailash, Chirag Delhi, Pushp Vihar and Saket are expected to get special benefits from this. After the launch of Metro, people of these areas will have to depend less on road transport for daily commuting. This will also make it convenient to reach nearby markets and business centres.
Interchange of three metro lines will be available in Lajpat Nagar
The biggest feature of this corridor will be its interchange stations. At Lajpat Nagar station, passengers will be able to change the metro between Pink, Violet and Golden Line. At the same time, interchange facility will be available between Magenta and Golden Line at Chirag Delhi station. There is a plan to connect Saket G Block station to the Aerocity-Tughlakabad corridor. This will provide better connectivity to passengers to reach the airport and other parts of Delhi.
Proposal to run three coach metro for the first time
Another special thing about this corridor is that for the first time it has been proposed to run a three-coach metro train on this route. Through this system, metro operation is being planned according to the passenger capacity and needs of the route.
Target to be completed by June 2029
Eight elevated stations will be built on the 8.385 km long corridor from Lajpat Nagar to Saket G Block. Of these, the contract for the construction of seven stations has been awarded for Rs 137.92 crore. The construction agency will have to complete the work in 22 months. The target has been set to complete the entire project by June 2029.
Underground metro will run from Rajiv Chowk in Gurugram to Yasobhoomi in Delhi.
The plan to build an underground metro corridor from Gurugram's Rajiv Chowk to Delhi's Yashobhoomi (Dwarka Sector-25) has received in-principle approval from the Delhi Government. Under this project costing about Rs 13,500 crore, a 20 km long underground metro track will be built. The project file prepared by Delhi Metro Rail Corporation (DMRC) has now been sent to the Union Urban Development Ministry. Construction work can start after getting final approval from the Union Cabinet. The project is targeted to be completed by the year 2031.
Underground metro corridor will be 20 kilometers long
The proposed corridor will connect Gurugram's Rajiv Chowk with Delhi's Yashobhoomi. There is a plan to build about 20 km long underground metro track on this route. Apart from Yashobhoomi, five other stations are also proposed on the route. The project is estimated to cost approximately Rs 13,500 crore. At present this proposal is in the process of approval at the central level.
One and a half lakh passengers will get benefit every day
It is estimated that after the opening of the corridor, about 1.5 lakh passengers will be able to use this metro service every day. This will make transportation between Gurugram and West Delhi easier. Especially the passengers going from Rajiv Chowk and surrounding areas towards Dwarka, Yashobhoomi and West Delhi will get a new transport option.
Currently direct connectivity is available on Yellow Line
At present, direct metro service is available from Delhi to Gurugram on the Yellow Line up to Millennium City Center metro station. However, once the proposed new corridor from Rajiv Chowk to Yashobhoomi is commissioned, commuters will get an additional route. This will increase the reach of the metro network between Gurugram and Delhi and can also help in reducing dependence on road transport.
Awaiting Union Cabinet approval
After the in-principle approval of the Delhi Government, the project file is now with the Union Urban Development Ministry. The construction process can be taken forward after getting the approval of the Union Cabinet.