How much cleaning work has been completed at Delhi's Ghazipur landfill site? When will the mountain of garbage end?

Plans to eliminate the mountain of garbage accumulated over decades at Delhi's Ghazipur landfill site have been slowed by legal hurdles and a tender dispute. The work on the third phase of the ambitious biomining project of the Municipal Corporation of Delhi (MCD) is currently stuck due to the Supreme Court's stay. The situation is such that about 69 lakh metric tonnes of old waste is still to be cleaned at the site. According to government data released in October 2026, a large amount of old waste is present at the Ghazipur landfill. At the same time, in the report released on November 22 by the Commission for Air Quality Management (CAQM), the progress of Ghazipur landfill has been described as the slowest among the major landfill sites of Delhi. The Commission has termed the garbage disposal situation here as 'unsatisfactory'.

Supreme Court ban on tender worth Rs 249 crore

A tender worth about Rs 249 crore was issued for biomining and redevelopment of land in the third phase of Ghazipur landfill. This contract was given to the lowest bidder Greentech Environment Management. However, the tender process ran into controversy over the company's previous blacklisting. The company was earlier blacklisted by the Gurugram Municipal Corporation for not meeting the set work targets and a fine of more than Rs 5 crore was also imposed on it. Later the company challenged this decision in Delhi High Court. After getting permission from the High Court to participate in the bidding process, Guru Ramdas Constructions, the second placed company, moved the Supreme Court. In October, the Supreme Court stayed the orders related to the case, due to which the work on the third phase could not begin. Delhi government has also demanded lifting of the ban in the court. The hearing scheduled for 23 November was further postponed by a week.

The Rs 249 crore tender for the third phase of biomining and redevelopment of the land was allotted to the lowest bidder, Greentech Environ Management, The Indian Express reported. Last week, the Standing Committee of the Municipal Corporation of Delhi (MCD) also approved this proposal.

Was earlier disqualified due to blacklisting

A controversy arose regarding the eligibility of Greentech Environment Management in this tender. Earlier, the Municipal Corporation of Gurugram (MCG) had blacklisted the company, due to which it was declared ineligible for the tender process. However, after the blacklisting was later withdrawn, the Delhi High Court allowed the company to participate in the bidding process.

Number two company reached Supreme Court

Challenging this order of the High Court, Guru Ramdas Constructions, the second bidder, approached the Supreme Court in October. Hearing the petition, the apex court stayed the tender process till further orders. Due to this, the work on the third phase of Ghazipur Landfill Project is currently stuck. Delhi government has also filed a petition to remove the Supreme Court ban. The matter was to be heard on Monday, but the court postponed the hearing for a week. Now the next hearing in the case is awaited.

The latest report of the Commission for Air Quality Management (CAQM) has described the progress of the Ghazipur landfill as unsatisfactory. As against the annual target set here, only 42 percent of the old waste has been disposed of by October 31, 2026.

According to the CAQM report, a target was set to dispose of 39.12 lakh metric tonnes of waste at the Ghazipur landfill site for the year 2026, but till October 31, only 16.53 lakh metric tonnes of waste could be processed. In this way only 42 percent of the target work has been completed. The special thing is that this figure does not include about 3,000 metric tons of new waste reaching Ghazipur landfill every day. This means that along with the disposal of old waste, the pressure of new waste is also continuously increasing.

Okhla and Bhalswa's progress is better than Ghazipur.

The situation at Ghazipur has been weak compared to other major landfill sites in Delhi. According to the report, Okhla landfill site has disposed of 67 per cent of its target, while Bhalswa has disposed of 57 per cent of the waste. The total combined target of the three major landfill sites of Delhi for the year 2026 was to dispose of 114.99 lakh metric tonnes of waste. In comparison, only 62.28 lakh metric tonnes of garbage could be cleaned till October 31. Thus, 52.71 lakh metric tons of waste still remains to be disposed.

Eyes fixed on the deadline of December 2027

A deadline of December 2027 has been set to completely remove the mountain of garbage from the Ghazipur landfill site. However, the Supreme Court's ban on the third phase biomining tender and the slow pace of the project have raised questions about this target. Despite this, sources associated with MCD claim that the project will be completed within the scheduled deadline of December 2027. According to officials, Alvazo Solutions JV, the agency that won the second phase tender, is currently carrying out waste disposal work at the site under an interim arrangement.