The Thang Long Project Management Board under the Ministry of Construction has approved the contractor selection results for the project’s feasibility study, with the winning consortium expected to complete the work within 30 months.
Nguyen Trung Son, deputy director of the board, said the consultancy consortium must meet four key milestones during the contract period.
By the third month, consultants must propose applicable technical standards and basic design requirements, establishing the foundation for subsequent surveys, calculations, and engineering work.
By the 13th month, they must submit an interim report proposing the route alignment, key control points, and technology options. These decisions will shape the project’s main technical solutions before the feasibility study is finalized.
By the 27th month, the feasibility study must be submitted to the appraisal council and the Ministry of Construction for review. The report is expected to receive final approval from relevant authorities by the 30th month.
|
A high-speed train arrives at a station in South Korea, April 2025. Photo by Dang Le |
From the first to the third quarter of 2027, the project owner will direct consultants and relevant parties to conduct topographical and geological surveys along the route. Land clearance boundaries will also be handed over to local authorities early to facilitate compensation, support, and resettlement work starting in 2027.
“Under this schedule, the project aims to break ground in late 2028,” Son said.
On Nov. 20, the board approved the contractor selection results for package TV-02, covering surveys, the feasibility study, front-end engineering design (FEED), and the preparation of bidding documents.
A Vietnamese-French-South Korean consortium won the contract with a bid of more than VND10.2 trillion ($400 million). The consortium comprises four foreign contractors, led by France’s SYSTRA alongside South Korea’s Sambo Engineering, Yooshin Engineering Corporation, and Korea National Railway.
Its Vietnamese members are Transport Engineering Design Inc. (TEDI), TEDI South, Transport Investment and Construction Consultancy JSC, and Hoang Long Construction Consultancy JSC.
Following approval of the selection results, the project management board invited the winning consortium to finalize the contract, with the signing ceremony expected by the end of November.
The 1,541-kilometer North-South railway will connect Ngoc Hoi Station in Hanoi with Thu Thiem Station in Ho Chi Minh City, passing through 15 provinces and cities. The double-track line will use the standard 1,435-mm gauge, with a design speed of 350 kph and an axle load of 22.5 tonnes.
The project will include 23 passenger stations and five freight stations, with preliminary total investment estimated at $67.34 billion.
The feasibility study is scheduled to be prepared and approved between 2026 and 2028, while the railway is expected to be substantially completed by 2035. The government had previously set a target of starting construction in late 2026.