Kachchi Dargah-Bidupur will be dedicated to the public on 21st November. 6-lane Nitish Setu, Raghopur Diara will be directly connected to the capital Patna.

Prime Minister Narendra Modi is going to hand over the 6 lane cable bridge (Nitish Setu) built on Ganga between Kachchi Dargah in Patna to National Highway No. 103 Bidupur in Vaishali to the public on November 21. This is the first time after independence, when the entire area of ​​Raghopur Diara situated on the other side of Ganga will be directly connected to the capital Patna by road. With the commencement of traffic on this ambitious bridge, along with direct connectivity between Kachchi Dargah, Raghopur Diara, Vaishali, it will also become easier for people to go to Samastipur and Darbhanga.

According to officials of the Road Construction Department, the construction work of a total of 19.76 km long 6 lane greenfield bridge project on the Ganga river between Kachchi Dargah located on National Highway No. 30 in Patna and Bidupur on National Highway No. 103 under Vaishali district has been completed. Under the project, a 9.76 km long bridge and 10 km long approach road have been constructed.

According to departmental officials, this six-lane bridge, built at a cost of Rs 5 thousand 571 crore 69 lakh, directly connects Sabalpur of Patna to NH-103 (Bidupur) along with Patna-Bakhtiyarpur Bypass (NH-30). With the completion of this bridge project, the people of this area will get uninterrupted road connectivity with the capital Patna. Agriculture, industry and other businesses will gain rapid momentum in this area. Also, in case of medical emergency, it has become convenient for the people who reach Patna for treatment. This entire project is proving to be extremely helpful in making the transportation between Patna and North Bihar fast, safe and easy. Once it is ready, the pressure of vehicles on Gandhi Setu will also reduce.

Important developments related to Nitish Setu

  • In the year 2012, the NDA government of the state envisioned a new 6-lane bridge on the Ganga.
  • In September 2012, the Infrastructure Development Authority (IDA) gave in-principle approval to the project.
  • In February 2013, instructions were given to appoint a transaction advisor and submit a possible report to the executing agency BSRDCL.
  • In June 2013, the alignment of the bridge was presented to the then Chief Minister Nitish Kumar.
  • In August 2014, the NDA government at the Center recommended a loan from ADB, on the basis of which a further loan agreement was signed.
  • In December 2014, the Ministry of Road Transport and Highways, Government of India gave NOC for the project.
  • In March 2015, a meeting was held on the construction of the new bridge under the chairmanship of the Secretary, Ministry of Road Transport and Highways.
  • International tender was invited for the construction of the bridge in July 2015 itself, after which a contract was signed with the construction agency and the construction work of the bridge started.
  • On 21 November 2026, PM Nitish will dedicate the bridge to the nation with his own hands.