8,922 modern ration buildings ready in UP, Yogi government increased the budget to Rs 500 crore

UP Annapurna Bhawan Scheme: Under the leadership of Uttar Pradesh Chief Minister Yogi Adityanath, the state government is working rapidly towards making the public distribution system (ration system) more transparent, strong and public convenience centric. 'Annapurna Bhawan Yojana', which was started to give a modern look to the fair price shops (government ration shops) of the state by taking them out of dilapidated and disorganized structures, has achieved remarkable success. According to the latest data of the Food and Logistics Department, the construction work of 8,922 Annapurna buildings has been completed so far in the state, while the construction of 2,377 buildings is going on at a fast pace.

The main objective of this ambitious initiative is to streamline the ration distribution system in rural areas, so that the beneficiaries can get food grains in a clean and safe environment and the Kotedars (fair price vendors) also have better infrastructure available for safe storage of grains.

How is Annapurna Bhawan and how much does it cost?

The construction of Annapurna buildings was started in the financial year 2023-24 in coordination with MNREGA and other government schemes. As per the standard design decided by the government, the total area of ​​each Annapurna building has been kept at 484 square feet. In this, along with two big rooms for storage and distribution of food grains, a verandah in front has also been arranged for the beneficiaries to stand. The estimated cost of construction of a building has been fixed at Rs 8.462 lakh.

Two and a half times increase in budget, from Rs 200 crore to Rs 500 crore

Seeing the success of the scheme, the Yogi government has made a big expansion in its budget. For the first time in the financial year 2025-26, an amount of Rs 200 crore was sanctioned from the departmental budget for this scheme. Under this, budget was allocated for the construction of 2,559 Annapurna buildings on the basis of action plans received from 71 districts. Now giving further impetus to this campaign, the government has increased the departmental budget to Rs 500 crore in the financial year 2026-27, which shows the government's commitment towards strengthening rural infrastructure.

Number of completed buildings increasing rapidly year after year

According to the report of the Food and Logistics Department, the pace of construction of Annapurna buildings in the state continues:

  • Financial year 2023-24: Construction of 3,808 buildings completed.
  • Financial year 2024-25: 3,502 buildings were completed.
  • Financial year 2025-26: Construction of 1,612 buildings was completed.

Thus, a total of 8,922 modern ration buildings have been completed in the state, while construction work on 2,377 other buildings is going on at various stages.

Government's strict monitoring on quality and timeliness

The construction works have been reviewed in detail in the report prepared for the review meeting to be chaired by the Chief Secretary. The first installment was released for 2,561 shops from the budget for the year 2025-26. Of these, 1,612 buildings have been completed (of which 871 structures are complete and 741 are at the finishing stage), while work on 725 buildings is in progress. Of these under-construction buildings, 386 are at roof level, 228 at linter level and 111 at foundation level.

The department has also prepared an action plan to soon start the construction of those 67 buildings whose work has not started yet. Along with this, accountability of officers is being fixed by keeping special monitoring in districts like Pratapgarh, Varanasi, Bijnor and Barabanki, where construction work is more pending.