Vietnam-France-South Korea consortium wins $400M high-speed rail consultancy contract

The Thang Long Project Management Board under Vietnam’s Ministry of Transport announced the results of contractor selection for package TV-02 on Sunday. The contract covers project surveys, preparation of a feasibility study incorporating Front-End Engineering Design (FEED), and development of bidding documents for the railway.

French engineering firm SYSTRA leads the winning consortium, which includes three South Korean members: Sambo Engineering, Yooshin Engineering Corporation and Korea National Railway.

The five other members are Vietnamese companies: Transport Engineering Design Inc. (TEDI), TEDI South, Transport Investment and Construction Consultant Joint Stock Company, and Hoang Long Construction Consultancy Company.

The consortium submitted a bid of more than VND10.243 trillion, below the initial estimated contract value of VND10.782 trillion. The contract has a planned duration of 30 months.

It was the only consortium to submit a bid by the Nov. 9 deadline.

A high-speed train in Germany. Photo by InterCityExpress

Following approval of the selection results, the Thang Long Project Management Board and the consortium will proceed with contract negotiations before signing the agreement.

Pham Huu Son, chairman of TEDI’s board of directors, said Vietnamese companies would undertake a substantial share of the work under the contract. He added that domestic firms had gained relevant experience through their involvement in design consultancy for the Hanoi-Quang Ninh high-speed railway project.

Package TV-02 is a key stage in preparing the North-South railway investment project. The selected consultant will conduct technical surveys and prepare the feasibility study, assessing options related to technology, investment structure, financing and economic viability.

The study will provide the basis for authorities to evaluate the project and make investment decisions. It will also examine opportunities to mobilize non-state funding, including domestic and foreign investment through public-private partnerships.

The consortium will also be responsible for developing the overall technical design and preparing bidding documents for subsequent construction and equipment installation packages. These tasks are intended to ensure technical consistency across the railway, reliable survey data and compliance with Vietnamese regulations and international standards.

The North-South high-speed railway is planned to span approximately 1,541 km, connecting Ngoc Hoi Station in Hanoi with Thu Thiem Station in Ho Chi Minh City, passing through 15 provinces and cities.

The proposed line will have double tracks with a standard gauge of 1,435 mm, a design speed of 350 kph and an axle load of 22.5 tonnes. It is expected to include 23 passenger stations and five freight stations.

The project’s preliminary total investment is estimated at $67.34 billion. Under the current timeline, the feasibility study is scheduled for preparation and approval between 2026 and 2028, with the railway expected to be substantially completed by 2035.

Leave a Comment