Bihar News: Action against agency on negligence in solar scheme, orders to speed up ration card work

Bihar News: Chief Secretary of Bihar suffix nectar A high-level review meeting of major public welfare schemes running in the state was held under the chairmanship of. In the meeting, special ration card campaign of Food and Consumer Protection Department and Energy Department was discussed. PM Surya Ghar Free Electricity Scheme The progress was reviewed in detail. The Chief Secretary directed the officers to speed up the work as well as to go to the area and see the actual status of the schemes.

13.93 lakh offline applications received

From across the state under the special ration card campaign. 13,93,704 offline applications Have met. After investigation these 11,83,792 applications eligible Have been found. Till 17th August 2026 4,13,079 applications i.e. 35 percent Data entry has been completed. In data entry, Jehanabad is ahead with 104 percent, Darbhanga with 102 percent, Arwal with 98 percent and Banka with 98 percent.

So far 13,292 applications for e-KYC Has been enabled for, out of which e-KYC of 1,569 has been completed. From SDO login till now 6,826 ration cards issued Have been done. Saharsa district has the highest 2,124 ration cards Have been issued. The Chief Secretary directed to expedite the ration card work and complete the pending e-KYC in mission mode.

5 lakh families benefited under PM Surya Ghar Yojana

PM Surya Ghar free electricity scheme was also reviewed in the meeting. Under the scheme, Bihar Cabinet on 12 August 2026 Additional state subsidy of ₹10,000 per KW and a maximum of ₹20,000 per beneficiary Has been approved. Total subsidy on 1 KW with Centre's CFA subsidy ₹40,000at 2 kW ₹80,000 and at 3 kW ₹98,000 Will be till.

spoil it first come, first serve 5 lakh will be given to the beneficiaries on the basis of Rs. State government for this ₹1,000 crore Will spend.

Target to install 5 lakh solar rooftops

Total for all districts on 14th August 5,00,000 solar rooftop installations A provisional target of Rs. 10,000 was fixed and field teams were sent. Patna has got the target of 28,000, East Champaran has got the target of 24,000 and Muzaffarpur has got the target of 23,000 installations.

Between 10th and 16th August 14,079 structuresi.e. an increase of 36 percent, and 6,690 solar panelsi.e. an increase of 48 percent, were imposed. total so far 35,879 structures and 14,656 panels Have been installed.

Many programs for awareness

To spread the information about the scheme to the people, tableaux are being organized at Gandhi Maidan in Patna, workshops in Darbhanga and Gaya, theater and radio advertisements in Purnia, Solar Rath Yatra in Jehanabad and Nawada and solar fairs are being organized in many districts.

Major action against negligent agency

Due to negligence and delay in work M/s Landsky Engineers Pvt. Ltd. LOA has been canceled and he has been debarred. The Chief Secretary clearly said that non-working agencies will not be spared under any circumstances.

He has pending for more than 7 days 132 inspections Directed to complete the inspection immediately and reduce the average time of inspection to less than 14 days. At present 12,407 structures and 17,610 panels are available in inventory while 13,200 structures and 3,112 panels Are on the way. The agencies have been asked to ensure continuous supply of material to meet the daily targets till November 2026.

All concerned in the upcoming review meeting Personal presence of Chief Engineers mandatory Has been done. The Chief Secretary has instructed the officers to visit the area and monitor the work and to implement the schemes within the stipulated time.