Rishikesh-Karnprayag Rail Project: Railways built a 6.59 KM long tunnel by digging the mountain.

Railways has brought good news for the people of Uttarakhand on Friday. A big target was achieved in the construction work of Rishikesh-Karnprayag Rail Project. The 6.59 km long Tunnel-14 of the project in Rudraprayag district has been connected at both ends to the main tunnel.

 

This tunnel connects 4.7 km dug from Portal-1 (Sumerpur) and 1.79 km dug from Portal-2 (Marora). According to the Railway Ministry, the tunnel was being excavated from Portal-1 of Sumerpur and Portal-2 of Marora. After digging 4.7 kilometers from one side and 1.79 kilometers from the other side, success has been achieved in connecting the two parts.

 

Also read: How did the son of a railway clerk become a millionaire? Vipul Vaibhav appeared before ED

Geological conditions made excavation a challenge

It has been told that digging in the weak geological conditions below the populated area was a big challenge. Railways has said that during tunnel excavation, special techniques were used to deal with challenges like safety of settlements, possibility of land subsidence, ventilation and temperature control.

 

 

The work of digging the tunnel in Rishikesh-Karnprayag Rail Project is being done by the government company RVNL and a private company. With this success, the construction work of Rishikesh-Karnprayag rail project is expected to gain significant momentum.

Main breakthrough of tunnel achieved

According to the Railway Ministry, the total length of Tunnel-14 is 6.59 kilometers. Its excavation was done from 4.7 kilometers from Portal-1 located in Sumerpur and 1.79 kilometers from Portal-2 located in Marora. The main breakthrough of the tunnel was achieved after the ongoing excavation on both sides was completed.

 

Also read: Recruitment for 2,861 apprentice posts starts in Railways, selection will be done without paper merit

What was challenging during the excavation?

The 110 meter long section of the triple-track tunnel beneath the populated area towards Portal-1 was excavated in challenging conditions. Here there was only a 20 to 30 meter layer of soil and rock above the tunnel. Special techniques like pre-excavation and multi-drifting were used for safe excavation.

 

At the same time, about 100 meters of mechanical excavation will be done on Portal-2 and controlled blasting will be done near both the portals only during the day to save the surrounding settlements. Special ventilation systems have been installed throughout the 4.7 kilometer Portal-1 drive for fresh air supply and temperature regulation.